SR 84 (Woodside Road) / US 101 Interchange Reimagined Project

Redwood City

Summary

The project is on track for construction in 2027 with a $350 million budget and a $105 million federal grant agreement pending execution. The council approved more design money but pressed the consultant on months-late cost reporting that led to a $2.8 million overrun.

At a glance

Total mentions
1
Last 30 days
0

Last discussed Jul 27, 2026.

Impact analysis

💰Financial impact

An additional $2.6 million in design costs raises the AECOM contract to roughly $15.7 million within a $350 million project budget.

✅Who benefits

Commuters and residents who use the congested Woodside Road/101 interchange.

⚠️Who could be affected

More than 600 trees will be removed for construction, starting this winter.

Mentions & discussions (1)

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Redwood City

What the council decided, in plain English — one email a week.

Also follow nearby cities

Free. Unsubscribe with one click any time. We never sell your email.