Maple Street Sewer Interceptor cost increase
Redwood City
Summary
The sewer line project needs more money — the council bumped the Cratus construction contract contingency from 10% to 18%, adding roughly $150,000 to finish the job.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Feb 23, 2026.
Impact analysis
Total authorized contract cost rises about $152,000, from $2,086,700 to $2,238,460.
Residents relying on the sewer system benefit from the interceptor's completion.