Summary
The lowest bidder, Sandstone Environmental Engineering, got the $545,300 demolition contract for the old senior center, a step toward the new Veterans Memorial/Senior Center project; the second-lowest bidder's protest was denied.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Discussed at 1 meeting in the last 60 days; most recently Sep 28, 2026.
Impact analysis
$545,300 contract, up to $654,360 with change orders.
Seniors move closer to the long-planned new Veterans Memorial/Senior Center facility.
Brannon Corporation, the second-lowest bidder, saw its bid protest denied.
Mentions & discussions (3)
City Council/Successor Agency/Public Financing Agency Regular Meeting - Sep 28, 2026
The lowest bidder, Sandstone Environmental Engineering, got the $545,300 demolition contract for the old senior center, a step toward the new Veterans Memorial/Senior Center project; the second-lowest bidder's protest was denied.
Veterans Memorial and Senior Center celebrates grand revamp
After nearly a decade of planning and pandemic-related construction delays, Redwood City leaders cut the ribbon outside the refurbished Veterans Memorial Building and Senior Center on Monday, alongside local veterans and former 49ers players who got their start at the facility.
City Council/Successor Agency/Public Financing Agency Regular Meeting - State of the City Address - Mar 23, 2026
The city celebrated the Hoover Park renovation — its biggest park investment in 30 years — expanding library programs, and announced the new Veterans Memorial Building and Senior Center opens May 4.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Redwood City
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.